The Régie du bâtiment du Québec (RBQ) exam for subcategory 1.7, Contractor – Telecommunications, transmission, transformation and distribution of electric power. Not sure which subcategory applies to you? See RBQ license: types, exams, costs and steps.
What do I get when I buy?
The full course: lessons, quizzes with explained answers and online review tools. Paid codes, standards or manuals cited in some quizzes are not included.
How long do I have access?
4 months from your enrolment in the paid course, anytime, as often as you like.
Can I try before I pay?
Yes. Create a free account, no credit card required: the first lessons are open right away. Buy only if the approach works for you.
How much does it cost?
$329 + taxes, one-time payment.
Is Prof-RBQ affiliated with the RBQ?
No. Prof-RBQ.ca is an independent exam-preparation centre, not affiliated with the RBQ or the CCQ. We have never seen the exam questions and do not guarantee success: the course covers the material described by the RBQ.
🎁 Try before you buy
Create your free account (no credit card required) and get immediate access to the first lessons of this course. Explore the lessons, try the quiz and see if our approach works for you. Purchase the course only if you're satisfied.
Get ready for your RBQ 1.7 electric power systems license with expert-designed practice tests. Access MCQs, Flashcards, and comprehensive explanations. Online course, available anytime for 4 months. Begin your exam preparation now!
Licence 1.7 at a glance
According to the RBQ, subclass 1.7 authorizes construction work on:
electric power transformation and telecommunications stations;
overhead and underground lines for electric power transmission, dispatching and distribution, and for telecommunication.
It also authorizes construction work in subclasses 3.1, 4.1, 5.1 and 6.1 of Schedule II when it relates to a civil engineering structure governed by this subclass, work in subclass 1.6 but only to have it carried out, and similar or related construction work.
Please note — This course prepares you for RBQ examinations. Its content is educational: before applying any concept on a job site, consult the codes and regulations in force, which take precedence in case of discrepancy. Some quizzes refer to paid codes, standards or manuals that are not included and may be required; they are available separately from their publishers. If you do not have the document a question refers to, simply skip that question. Prof-RBQ is independent of the RBQ and does not guarantee exam success.
Format
Online course
Start
Now
Duration
4 months
Course Lessons
RBQ 1.7 — Contractor – Telecommunications, transmission, transformation and distribution of electric power: preparation for the Régie du bâtiment du Québec exam. Lessons, a bank of practice questions and flashcards, built on the law in force, Hydro-Québec standards and specifications and the Safety Code for the construction industry. The exam: 3 hours, 60%, closed book.
1. The RBQ 1.7 licence
Subclass 1.7 is in Schedule I of the Regulation respecting the professional qualification of contractors and owner-builders (chapter B-1.1, r. 9). It authorizes construction work relating to electric power transformation and telecommunications stations and overhead and underground lines for electric power transmission, dispatching and distribution, and for telecommunications. It also authorizes construction work in subclasses 3.1, 4.1, 5.1 and 6.1 of Schedule II when it is related to civil engineering structures covered by this subclass, and construction work in subclass 1.6, but only to have it carried out and only when it is related to civil engineering structures covered by this subclass. Lastly, it authorizes similar or related construction work. According to the competency profile, construction and grounding work on private stations (a plant or a commercial building, for example) falls under subclass 16, electrical contractor.
The licence is issued by the Régie du bâtiment du Québec under the conditions of the Regulation respecting the professional qualification of contractors and owner-builders (chapter B-1.1, r. 9), including the qualification of the respondent. Prof-RBQ.ca prepares candidates for the subclass exam; it awards no credential.
2. Who this course is for
The contractor who builds or repairs overhead or underground lines, substations or telecommunications structures for Hydro-Québec, another system operator or a telecommunications carrier.
The project manager, estimator or superintendent who intends to act as the respondent of the company's licence.
The candidate who worked under the former prevention regime and must catch up on the modernized Act respecting occupational health and safety.
3. Exam format: what to expect
Type of questions: multiple-choice questions
Duration: 3 hours
Pass mark: 60%
Language: in French or in English
Documentation: closed book — only the documents and materials provided by the invigilator may be used
This information comes from the RBQ 1.7 exam information sheet (Update: 2020). The sheet publishes neither the number of questions nor the weight of each section.
4. Documentation: all recommended reading
The sheet names eleven documents (Acts, codes and regulations), all listed as recommended reading: according to the sheet (Update: 2020), none of them is marked as provided at the exam. What they say must be known before you walk in.
Building Act (chapter B-1.1)
Regulation respecting the professional qualification of contractors and owner-builders (chapter B-1.1, r. 9)
Civil Code of Québec
Criminal Code, section 217.1
Engineers Act (chapter I-9)
Act respecting labour relations, vocational training and workforce management in the construction industry (chapter R-20)
Cultural Heritage Act (chapter P-9.002)
Environment Quality Act (chapter Q-2)
Regulation respecting compensation for adverse effects on wetlands and bodies of water (chapter Q-2, r. 9.1)
Regulation respecting the environmental impact assessment and review of certain projects (chapter Q-2, r. 23.1)
Sustainable Forest Development Act (chapter A-18.1)
The competency profile also refers to the Safety Code for the construction industry (chapter S-2.1, r. 4), to Hydro-Québec standards and specifications and to the Canadian Welding Bureau. The course covers them to the extent that the profile refers to them.
5. The seven sections of the competency profile
Competency profile 1.7 has 25 elements of competency and 95 skills, in seven modules that the exam sheet takes up as sections. The RBQ does not publish their weighting.
Section 1 — Specific definitions and principles (17 skills, 5 lessons)
Section 2 — Specific legislative, normative and regulatory framework (8 skills, 3 lessons)
Section 3 — Reading and interpreting specific plans and specifications (8 skills, 2 lessons)
Section 4 — Cost estimates and bids for a specific project (9 skills, 2 lessons)
Section 5 — Management of specific construction activities (14 skills, 2 lessons)
Section 6 — Execution of construction work (14 skills, 4 lessons)
Section 7 — Specific prevention management (25 skills, 4 lessons)
6. What the preparation includes
22 lessons linked to the skills of the profile, each with its figures, its traps and, where the law has changed since 2020, a “What has changed” box.
598 practice questions (multiple choice), 138 of which are based on 102 diagrams; each explanation gives its reference.
9 quizzes: one per section, which presents all the questions of the section in random order; a mock exam of 100 questions drawn 18 · 9 · 8 · 9 · 15 · 15 · 26 per section; a free trial quiz of 14 questions.
269 flashcards to fix the terms, values and thresholds.
7. Five mechanisms a 1.7 contractor must tell apart
A few points the preparation insists on, because they turn on a fine distinction rather than on general knowledge:
The voltage is read between phases. The Safety Code for the construction industry sets the minimum approach distance by range of voltage between phases (s. 5.2.1): 3 m for less than 125,000 V, 5 m from 125,000 to 250,000 V, 8 m from 250,000 to 550,000 V, 12 m for more than 550,000 V. A three-phase line of 150 kV between phases has about 87 kV between one phase and the ground, but it is the 150 kV that is read: 5 m, not 3 m. The Code excludes certain work from its Division V on power lines (s. 5.1.2), including the construction, repair or maintenance of an electrical line by a worker of the electrical power company or by an employer authorized by it.
Thirty metres is not an approach distance. Within 30 m of a line of more than 250,000 V, s. 5.2.3 adds three requirements: refuelling is done outside the area; construction equipment on tires has an electrostatic link between its metallic part and the ground; any metal duct, fence or above-ground structure being installed or handled is grounded every 30 m. At 20 m from a 735 kV line, you are beyond the 12 m, but inside the area.
Any other civil engineering structure. A line, a substation or a conduit system of an electric power transmission or distribution system falls under “any other civil engineering structure” (Building Act, s. 2, paragraph 5): the Building Act applies to it only for the purposes of Chapters IV and V, the licence and the financial guarantees; the other Acts that govern the job site, such as the Act respecting occupational health and safety, still apply. An electrical installation independent of a building, a customer's private installation for example, falls under paragraph 3: the whole Building Act applies to it. The structure must be classified before concluding.
Thresholds are read at the foreseen peak. The prevention mechanisms of the job site are triggered by the number of workers foreseen simultaneously, not by the average: 10 for the prevention program and the health and safety representative, 20 for the job-site committee, 100 — or a total cost of the work of more than 12 million dollars, the amount in the version consulted in October 2026, which the Act provides is revalorized every five years, on 1 January — for the health and safety coordinator and the full-time representative. These thresholds trigger specific mechanisms; below them, the general obligations of the Act still bind the employer and the principal contractor (ss. 51 and 196).
Three metres is the barricade, not the shoring. Depth does not exempt a trench from shoring: shoring is not required in three cases only — a trench dug out of solid rock or one into which no worker is required to descend; banks with no risk of collapsing that slope less than 45° from a point less than 1.2 m from the bottom; banks with no risk of collapsing and an engineer's attestation (s. 3.15.3). Continuous barriers or barricades at least 0.7 m high, or a warning line as provided for in s. 2.9.4.1, on the other hand, are required at the edge of any digging more than 3 m deep and also, at any depth, of any digging that might constitute a hazard to workers or the public (s. 3.15.5).
8. Preparation strategy
Retain what governs. In a closed-book exam, the skill to work on is carrying the values that decide — distances, thresholds, time limits, proportions — and knowing which one applies to the situation described. The explanations name the section or clause, because a number attached to a rule is a number that stays.
One section at a time, then the whole. The section quizzes first, then the mock exam. A section quiz presents all the questions of the section in random order, the mock exam draws its questions at random, and the order of the answers changes from one attempt to the next. Retake each quiz several times, over several days. The flashcards help fix the values.
9. Our sources and their editions
The questions are written from documents we consulted, and their explanations give the reference: Québec Acts and regulations, the Safety Code for the construction industry, Hydro-Québec standards and specifications, the CERIU guide, CNESST and ASP Construction guides, and the RBQ competency profile and exam information sheet.
The editions. Our questions were developed from the Québec Acts and regulations in their consolidated versions consulted in October 2026 on LégisQuébec, including the 2026 orders in council that affect the job site — O.C. 816-2026 (concrete pumps) and O.C. 817-2026 (Safety Code for the construction industry), in force on 10 August 2026, O.C. 37-2026 (first aid) and O.C. 38-2026 (qualification of contractors) — and from the standards and specifications published by Hydro-Québec and the CERIU guide in the edition consulted, named in each explanation. Where the English version of a provision differs from the French version or has not yet been updated, the course follows the French version. The CSA standards for overhead and underground systems (C22.3 series) are not free of charge; the course takes no value from them and does not require them. The RBQ may rely on other editions.
We have not seen the RBQ's question bank: the preparation is based on the subject matter described in the official profile; it does not predict the exam questions.
Frequently asked questions
What work does RBQ licence subclass 1.7 cover?
The Regulation respecting the professional qualification of contractors and owner-builders (chapter B-1.1, r. 9) places subclass 1.7 in Schedule I, among the general contractor subclasses. It authorizes construction work relating to electric power transformation and telecommunications stations and overhead and underground lines for electric power transmission, dispatching and distribution, and for telecommunications. It also authorizes construction work in subclasses 3.1, 4.1, 5.1 and 6.1 of Schedule II when it is related to civil engineering structures covered by this subclass, and construction work in subclass 1.6, but only to have it carried out and only when it is related to civil engineering structures covered by this subclass. Lastly, it authorizes similar or related construction work. According to the competency profile, construction and grounding work on private stations (a plant or a commercial building, for example) falls under subclass 16, electrical contractor.
How long is the RBQ 1.7 exam and what is the pass mark?
According to the Régie's exam information sheet (Update: 2020), the exam lasts 3 hours, consists of multiple-choice questions and the pass mark is 60%. It can be taken in French or in English. The sheet does not give the number of questions.
Is the RBQ 1.7 exam open book?
No, it is closed book. The eleven documents named on the exam information sheet are all listed as recommended reading and none is marked as provided at the exam; only the documents and materials provided by the invigilator may be used; the materials required (calculator, ruler, paper, pencil) are provided on site. Everything is therefore studied before the exam.
How is the exam divided among the seven sections?
The RBQ publishes no weighting. The sheet describes seven sections, which follow the seven modules of the competency profile (95 skills in all). Our 100-question mock exam draws 18 · 9 · 8 · 9 · 15 · 15 · 26 questions per section, a distribution close to each section's share of skills in the profile. This is our choice, not official data.
Are the competency profile and the exam sheet still up to date?
Only in part. The exam sheet bears the mention “Update: 2020”, and the competency profile is not dated. Since 1 January 2023, the organization of safety on a construction site no longer falls under subdivision 2.5 of the Safety Code for the construction industry, which was revoked, but under the modernized Act respecting occupational health and safety (chapter S-2.1) and the Regulation respecting prevention mechanisms specific to construction sites (chapter S-2.1, r. 8.2): prevention program, job-site committee, health and safety representative, health and safety coordinator. Other texts have been substantially amended, including Act R-20 in 2024. The course teaches the law in force and flags these changes in the lessons.
Is a Hydro-Québec line or substation subject to the whole Building Act?
Not in full. Section 2 of the Building Act distinguishes electrical installations independent of a building (paragraph 3), subject to the whole Act, and any other civil engineering structure (paragraph 5), subject to it only for the purposes of Chapters IV (vocational qualification, hence the licence) and V (financial guarantees); the other Acts that govern the job site, such as the Act respecting occupational health and safety, still apply. The lines, substations and conduit systems of an electric power transmission or distribution system fall under paragraph 5; an electrical installation independent of a building, such as a customer's private installation, falls under paragraph 3. The structure must therefore be classified before concluding.
What distance must be kept from an overhead power line?
The Safety Code for the construction industry (chapter S-2.1, r. 4), s. 5.2.1, sets the minimum approach distance according to the voltage between phases: 3 m for less than 125,000 V, 5 m from 125,000 to 250,000 V, 8 m from 250,000 to 550,000 V and 12 m for more than 550,000 V. A 25 kV line between phases therefore calls for 3 m, a 315 kV line, 8 m. Working closer is permitted only in the cases provided for by the Code, with all their conditions. The Code excludes certain work from its Division V on power lines (s. 5.1.2), including the construction, repair or maintenance of an electrical line by a worker of the electrical power company or by an employer authorized by it.
What does the Prof-RBQ.ca preparation for licence subclass 1.7 include?
22 lessons on the seven sections, a bank of 598 practice questions from which the quizzes draw, 138 of which are based on 102 diagrams, 9 quizzes (one per section, a 100-question mock exam and a free 14-question trial quiz) and a set of 269 flashcards.
What is a diagram question?
A question whose answer is read on a project document or a drawing: a system diagram, a section of a duct bank or trench, a conduit system plan, a schedule of prices, a workforce calendar or a job-site scene. The markers are designed to stay neutral and not give the answer away: the diagram must be interpreted.
Does the course cover Hydro-Québec specifications and clauses?
Yes, to the extent that the competency profile refers to them: reading plans and specifications, quantity survey, estimating and bidding, quality control. The questions then specify that the requirement comes from a Hydro-Québec specification, not from an obligation under the law.
How do you prepare effectively for a closed-book exam?
Retain the values that govern — approach distances, workforce thresholds, time limits, proportions — and know which one applies to the situation described. Do the section quizzes before the mock exam, without documents, and read each explanation even when you get it right: it gives the rule, its reference and the neighbouring value it is confused with. The flashcards help fix these values.
Does the course replace the Acts and the official texts?
No. It is a preparation and review tool. It replaces neither the Acts and regulations nor the standards and specifications, and it is neither legal advice nor technical advice. If an explanation and the official text differ, the official text prevails.